Here’s something nobody quite prepares you for. You sign for a new-build home at one price. Then, over the next year and a half, the money leaves — or rather, your mortgage releases it — in pieces. A bit now. A larger bit a few months later. Another piece when something you can’t see has been finished somewhere on a building site.

This is termijnbetalingen: paying for your home in instalments, as it gets built. It’s completely standard, it’s legally protective, and almost nobody explains the shape of it before you’re already inside it. So here’s the rhythm.

Two prices, paid two different ways

Your new-build actually has two prices hiding inside one total, and they’re paid in completely different ways.

De grond
The land

Paid in full, once, at the notary on the day you legally become the owner. This part of your mortgage is drawn immediately.

De aanneemsom
The construction sum

Paid in instalments — termijnen — across the whole build, each one released as a stage of construction is completed.

The land is a single transaction. The construction sum is a slow drip across 18 to 24 months. When people say their nieuwbouw payments “keep coming,” this is what they mean — and it’s the mechanism underneath the rising monthly payment we wrote about in your nieuwbouw mortgage isn’t the mortgage you’ll live with.

What a termijn actually is

A termijn isn’t a date on a calendar. It’s a milestone in the build. The contractor reaches a defined point — the foundation is poured, the structural shell is up, the exterior brickwork is done — and that completion triggers an invoice for a fixed percentage of the construction sum.

The key idea

You’re not paying on a schedule of dates. You’re paying on a schedule of progress. The order is fixed in your contract. The timing floats with the building site.

Because the trigger is physical progress, the law is firm on one point: payments must follow the work, never lead it. The contractor can’t bill you for a stage that isn’t finished — and you shouldn’t pay for one that isn’t.

How many instalments, and how big

The number of termijnen depends on what you’re buying. A single-storey house is divided into fewer stages than a six-storey apartment building. For homes covered by an SWK or Woningborg guarantee — which is most of them — the institute prescribes the exact number and the exact moments.

5–11
instalments (termijnen), depending on house type and number of floors
≤10%
the first instalment, due at the start of construction
2 wks
to pay each invoice once it lands, before penalties apply

A traditional house or apartment typically lands around eight termijnen. The shape of a common schedule looks roughly like this — the exact percentages vary by project, but the pattern is consistent:

  1. Start of construction — around 8% of the construction sum.
  2. Foundation complete — around 10%.
  3. Structural shell up — the big one, often around 40% in a single invoice.
  4. Exterior brickwork complete — around 30%.
  5. Oplevering (handover) — the final ~10%, due before you get the keys.

Notice where the weight sits. The structural shell is the single largest payment — often close to half the construction sum in one invoice. That’s the moment your bouwdepot (the construction account your mortgage set aside) empties fastest.

You almost never wire the money yourself

Here’s the part that surprises buyers who brace themselves to make these payments. In most cases, you don’t make them directly.

When a termijn falls due, the contractor sends the invoice. You forward it to your mortgage lender, and the lender pays the contractor straight out of your bouwdepot. Your job is mostly to check the invoice matches real progress, then pass it on promptly. The money moves from a pot that’s already yours, set aside for exactly this.

The one deadline that’s genuinely yours: once an invoice arrives, you have roughly two weeks to pass it on and have it paid. Miss it and you owe boeterente — penalty interest, at a rate set in your contract. The build runs on no deadline you control. This one you do.

Meerwerk and finishing run on a separate track

Everything so far covers the aanneemsom — the base house. But two of the costs that hurt most sit outside that termijn schedule: meerwerk (your upgrades — the better kitchen, extra sockets, the dakkapel) and the afbouw (finishing). They’re billed on their own clock, and some of it can’t come from your bouwdepot at all.

Meerwerk is settled separately from the termijnregeling. Typically you pay a portion when you confirm the order and the balance before oplevering — and every meerwerknota has to be paid before you get the keys, the same hard line as the final termijn.

Then comes the part that catches people: not all of it can be financed. Your bouwdepot holds the mortgage money set aside for the grond, the termijnen, and eligible meerwerk and finishing — but two limits bite.

From the bouwdepot
Financed

The termijnen, plus meerwerk and finishing that’s permanently fixed to the home — tiling, sanitary, taps, a glued floor. Released against invoices, up to your lender’s meerwerk cap.

From your own pocket
Cash

Meerwerk above that cap, plus anything you could take with you — loose flooring, curtains, lighting, furniture. Not depot-eligible. Paid in cash.

Lenders cap how much meerwerk you can fold into the mortgage (meefinancieren), and the cap varies by lender — some finance only part of it. That makes one number worth having before you walk into koperskeuzes: how much of your wish list your mortgage can actually carry. Your mortgage advisor sets it — worth knowing your number before you start choosing.

And the timing stings. This cash demand tends to land late — around oplevering — which is exactly when your double housing costs are at their peak, the squeeze we covered in the mortgage piece. One more quiet cost: whatever’s left unused in the depot at the end doesn’t come back to you as cash. It’s deducted from your mortgage — money you’d earmarked for the home, gone.

If you buy after the build has started

Not every buyer signs before the first shovel goes in. If you buy into a project that’s already under construction, the termijnen that have already passed don’t disappear — you pay them in one go at the notary, alongside the land. On top of that you may owe bouwrente: interest the developer charges on the instalments that fell due before you became the owner.

It’s not a penalty and it isn’t hidden, but it’s a real number that catches late entrants off guard. If you’re buying a home where construction is already visible, ask exactly which termijnen are already due and what bouwrente applies before you sign.

The last termijn, and a right worth knowing

The final instalment falls due at oplevering — handover — and must be paid before you receive the keys. But you don’t have to pay all of it blind.

Dutch law gives you the 5%-regeling: the right to hold back 5% of the construction sum at handover and park it with the notary, as security against defects found during the inspection. The contractor only receives it once those points are resolved. It’s one of the strongest protections a nieuwbouw buyer has — and most people find out about it the day before, when it’s too late to use properly. It’s worth its own article, and it’ll get one.

What to actually do

  • When you sign, find the termijnschema in your koop-/aannemingsovereenkomst and read how many instalments there are and what triggers each.
  • Treat every invoice as a two-week task, not a someday task. Forward it to your lender promptly and confirm it’s been paid from your bouwdepot.
  • Before koperskeuzes, ask your mortgage advisor how much meerwerk you can finance — and budget cash for the finishing your depot won’t cover.
  • If you’re buying mid-build, get the list of already-due termijnen and any bouwrente in writing before the notary.
  • Plan for the 5%-regeling now, not on the morning of handover.

The rhythm isn’t random

Termijnbetalingen feel like money disappearing on someone else’s schedule — because, in a sense, it is. But the schedule isn’t arbitrary. Every instalment is tied to something real being finished, every payment is protected precisely because it follows the work, and the one deadline that lands on you is small and entirely manageable once you know it’s coming.

The payments were never the hard part. Not knowing the rhythm was.