Here's a moment that confuses almost every nieuwbouw buyer. You've signed the koop-/aannemingsovereenkomst. You're excited. And then nothing happens. No construction. No date. No confirmation that the project is even going ahead.

What you're experiencing has a name: opschortende voorwaarden. They're the reason your purchase isn't final yet — and the reason the build clock hasn't started. They're not a problem. They're a safety mechanism. But because nobody explains them, they just feel like silence.

First: don't confuse the two kinds of conditions

Dutch new-build contracts contain two types of conditions, and buyers mix them up constantly. They sound similar, they're one concept apart, and they do opposite things.

Ontbindende voorwaarden
Resolutive conditions

Protect your exit. Usually financing — you get a set period to arrange your mortgage. If you can't, you walk away penalty-free. This one works in your favour.

Opschortende voorwaarden
Conditions precedent

Delay the start. The contract is signed but doesn't take full effect until certain project conditions are met. This one is about whether the project happens at all.

One protects your way out. The other delays everything coming in. This article is about the second.

What the conditions usually are

The opschortende voorwaarden written into most nieuwbouw contracts are remarkably consistent across developers. The most common:

  • A minimum number of homes sold — typically 70% of the project. Until enough buyers commit, the developer won't start building.
  • An irrevocable building permit (onherroepelijke omgevingsvergunning) — the municipality must grant it, and any objection periods must have passed.
  • The land must be build-ready (bouwrijp) and owned by the selling party.
  • A warranty registration number — from SWK, Woningborg, or BouwGarant, confirming your future home is covered by a guarantee scheme.

Some projects add their own: a nature-protection permit (Wet natuurbescherming), a go/no-go decision date, or other project-specific triggers. They'll be listed in your contract.

Why they exist — and why that protects you too

The obvious beneficiary is the developer. No one can responsibly start construction on a half-sold project — the financial exposure is enormous. The 70% threshold exists to limit that risk.

But the conditions protect you just as much. If the project never reaches viability — not enough buyers, no permit, an unresolved objection — you are not locked into buying into a development that stalls or collapses. If the conditions aren't met by the deadline, the agreement dissolves and your deposit comes back. You're held in place only until everyone knows the project is real.

The key idea

Until the opschortende voorwaarden are met, you have a signed contract that hasn't taken effect yet. The moment they're met, the contract becomes unconditional — and that's when your real timeline begins.

What can make the conditions fail — and how often it happens

The conditions exist precisely because projects sometimes don't reach viability. So how often do they actually fail?

The honest answer: nobody publishes the number you'd actually want. Only SWK and Woningborg — the two warranty institutes that register every project — would know how many signed agreements dissolve because the conditions weren't met in time. Neither publishes it. So if anyone quotes you a precise "failure rate," treat it with suspicion.

What we can see is the project-level picture, and it tells you the risk is real. In 2023 — the worst recent year — developers reported thousands of planned homes postponed.

7,477
homes documented as delayed in 2023 (Capital Value survey)
~40,000
homes flagged at risk of postponement, 2023–2024
−50%
drop in new-build sales to private buyers, 2021 to 2022

The industry body NEPROM said in early 2023 that some of its members saw up to half their projects delayed. Sales of new-build homes to private buyers roughly halved between 2021 and 2022 — from about 36,000 to 20,000 — and fell further in 2023.

The most common reasons a project stalls or dies, roughly in order of how often they're cited:

  1. Not enough homes sold — the ~70% pre-sale threshold isn't reached in time.
  2. Mortgage rates rising — which suppresses buyer demand and causes the first one. Rates went from around 1% to over 4% during 2022.
  3. Construction costs climbing until the project is no longer financially viable for the developer.
  4. Permit objections — neighbours or other parties challenging the omgevingsvergunning, sometimes for years.
  5. Nitrogen rules (stikstof) — which froze permit approvals across several provinces.
  6. Grid congestion (netcongestie) — connection waits stretching to 40 weeks or more.

The encouraging part: 2024 and 2025 show a clear recovery, with new-build sales rebounding strongly. But the nitrogen and grid-capacity problems are structural, and delays haven't disappeared. The risk is lower than it was in 2023 — not gone.

What this means for your timeline

This is the part buyers feel without understanding. After signing, there's a stretch — typically up to nine months — where the conditions are being satisfied. During this period there's often no visible construction and no firm handover date. That's normal. That's the opschortende voorwaarden period.

Crucially: the construction time quoted in your contract — the bouwtijd, often expressed as a number of working days — does not start counting from your signature. It starts from the moment the conditions are lifted and you receive written notice that the agreement has become unconditional.

There's a second-order effect that catches people. Your financing reservation — the ontbindende voorwaarde — often only starts when the opschortende voorwaarden are met. With some developers you get roughly two months from that moment to secure your mortgage offer. So the two clocks are linked: the start of your financing deadline depends on when the project becomes unconditional.

One thing worth knowing about extensions

If the conditions aren't met within the agreed term, the developer can request an extension. They cannot impose one. Your consent is required — and at that decision point, you're typically free to walk away from the agreement at no cost.

That's real leverage most buyers don't realise they hold. If a project is dragging far past its expected timeline, the extension request is a genuine decision point, not a formality to rubber-stamp.

And if the conditions genuinely aren't met? The contract dissolves, there's no penalty, and your deposit or bank guarantee is returned in full. The one real risk that lands on you: if the developer requests an extension and your mortgage offer expires in the meantime, you may face higher rates or have to requalify under current lending rules. That cost isn't covered by anyone — which is exactly why the validity date on your hypotheekofferte matters so much during this period.

What to actually do

  • Find the opschortende voorwaarden clause in your contract and read exactly which conditions apply and what the deadline is.
  • Don't assume construction starts when you sign — ask the developer what's still outstanding and how many homes are sold.
  • Track the "onvoorwaardelijk" moment — the written notice that conditions are met. That's when your build clock and often your financing clock begin.
  • Mind your mortgage offer's validity. Because this period can run months, your hypotheekofferte must still be valid on the day you sign at the notary — or you'll face an extension fee.

The silence has a name now

Opschortende voorwaarden aren't an obstacle in your way. They're the mechanism that keeps you from being locked into a project that isn't real yet. The frustrating part was never the conditions themselves — it was that nobody told you they were there, or what they meant.

Now you know what the silence after signing actually is. And you know which date to watch for.